Mt Milligan Copper/Gold Project
Location: Fort St James, BC
Graham scope of work included the construction of a 105’ high Primary Crusher structure used to process the ore material, construction of the ore reclaim tunnel and foundations with walls and slabs, completion of the construction of the pebble crushing house and slab, construction of the grinding area, flotation and concentrator building foundations and elevated slabs. Along with this work there were some other small foundations and slabs completed throughout the plant site.
In total, Graham supplied and installed of 46,800 m3 of concrete that was used to build this new copper gold mine. Graham self-performed all concrete work and leveraged its own fleet of equipment.
Contract Value
$93M CAD
Prime Consultant
–
Project Owner
Terrane Metals Corp
Contract Format
Stipulated Price
Completion Date
Feb 2013
Contract Duration
20 months