BCIT Student Plaza Revitalization

Location: Burnaby, BC

The intent for this enhancement project was to improve the pedestrian environment and create a gateway space that showcases a clear entry at BCIT’s Burnaby Campus and create a social hub for the campus.

The space includes improved pedestrian flow, weather protection, a clear key arrival place on campus, and utilizes sustainable features including efficient water irrigation systems and the unique, one-off design of a cantilevered Mass Timber canopy composed of a cross-laminate timber (CLT) roof deck and a combination of steel and CLT columns.

The scope of this new landmark gateway within the existing BCIT Burnaby campus included:

  • Civil works including all underground services and relocation of services
  • New paving stones walkway throughout the site
  • Improved wayfinding
  • Custom landscaping with specialized benches that include wifi bollards
  • 300ft Mass Timber canopy

Contract Value

$6.5M CAD

Prime Consultant

HCMA Architecture & Design

Project Owner

British Columbia Institute of Technology

Contract Format

Lump Sum

Completion Date

May 2023

Contract Duration

7 months