Cory Red Product Expansion
Location: Saskatoon, SK
Graham’s work consisted of a prime mechanical, civil, piping and site services contract for the work related to the 1.8 million-tonne-per-year expansion of the Cory Potash Red product mine. Civil work included the supply and installation of all concrete works for the new compaction plant, wet mill, ore load-out, and miscellaneous upgrades in the existing white mill.
In addition, there was the design-build of a 10,405 m2 product storage warehouse, constructed with concrete foundations and buttress works, pre-cast wall panels and a wooden arched laminated glulam structure, as well as the excavation, supply and installation of a 213-metre concrete reclaim tunnel. It is anticipated that 15,000 m3 of concrete and 9,000 m3 of fillcrete will be poured in this project.
Contract Value
Undisclosed
Prime Consultant
AMEC Americas
Project Owner
Nutrien
Contract Format
Design-Build
Completion Date
May 2010
Contract Duration
–